  1. Monitoring facilities. The installation of a monitoring facility shall be required for all industrial users. A monitoring facility shall be a manhole or other suitable facility approved by the city.

    When in the judgment of the city there is a significant difference in wastewater constituents and characteristics produced by different operations of a single user the city may require that separate monitoring facilities be installed for each separate source of discharge.

    Monitoring facilities that are required to be installed shall be constructed and maintained at the user's expense. The purpose of the facility is to enable inspection, sampling and flow measurement of wastewater produced by a user. If sampling or metering equipment is also required by the city, it shall be provided and installed at the user's expense.

    The monitoring facility will normally be required to be located on the user's premises outside of the building. The city may, however, when such a location would be impractical or cause undue hardship on the user, allow the facility to be constructed in the public street right-of-way with the approval of the public agency having jurisdiction of that right-of-way and located so that it will not be obstructed by landscaping or parked vehicles.
    There shall be ample room in or near such sampling manhole or facility to allow accurate sampling and preparation of samples for analysis. The facility, sampling, and measuring equipment shall be maintained at all times in a safe and proper operating condition at the expenses of the user.

  2. Inspection and sampling. The city shall inspect the facilities of any user to ascertain whether the purpose of this chapter is being met and all requirements are being complied with. Persons or occupants of premises where wastewater is created or discharged shall allow the city or their representative ready access at all reasonable times to all parts of the premises for the purpose of inspection, sampling, records examination or in the performance of any of their duties. The city, approval authority and EPA shall have the right to set up on the user's property such devices as are necessary to conduct sampling inspection, compliance monitoring and/or metering operations. Where a user has security measures in force which would require proper identification and clearance before entry into their premises, the user shall make necessary arrangements with their security guards so that upon presentation of suitable identification, personnel from the city, approval authority and EPA will be permitted to enter, without delay, for the purposes of perform in their specific responsibility.
  3. Compliance date report. Within one hundred eighty (180) days following the date for final compliance with applicable pretreatment standards or, in the case of a new source, following commencement of the introduction of wastewater into the POTW, any user subject to pretreatment standards and requirements shall submit to the city a report indicating the nature and concentration of all pollutants in the discharge from the regulated process which are limited by pretreatment standards and requirements and the average and maximum daily flow for these process units in the user facility which are limited by such pretreatment standards or requirements. The report shall state whether the applicable pretreatment standards or requirements are being met on a consistent basis and, if not, what additional O&M and/or pretreatment is necessary to bring the user into compliance with the applicable pretreatment standards or requirements. This statement shall be signed by an authorized representative of the industrial user, and certified to by a professional engineer registered to practice engineering in Tennessee.
  4. Periodic compliance reports.


    1. Any user subject to a pretreatment standard, after the compliance date of such pretreatment standard, or, in the case of a new source, after commencement of the discharge into the POTW, shall submit to the city during the months of June and December, unless required more frequently in the pretreatment standard or by the city, a report indicating the nature and concentration of pollutants in the effluent which are limited by such pretreatment standards and requirements.

      In addition, this report shall include a record of all daily flows which during the reporting period exceeded the average daily flow. At the discretion of the city and in consideration of such factors as local high or low flow rates, holidays, budget cycles, etc., the city may agree to alter the months during which the above reports are to be submitted.

    2. The city may impose mass limitations on users where the imposition of mass limitations are appropriate. In such cases, the report required by subsection (4)(a) shall indicate the mass of pollutants regulated by pretreatment standards in the effluent of the user.
    3. The reports required by this section shall contain the results of sampling and analysis of the discharge, including the flow and the nature and concentration or production and mass where requested by the city of pollutants contained therein which are limited by the applicable pretreatment standards. The frequency of monitoring shall be prescribed in the wastewater discharge permit or the pretreatment standard. All analysis shall be performed in accordance with procedures established by the administrator pursuant to § 304(g) of the Act, being 33 U.S.C. § 1314(g), and contained in 40 CFR, and amendments thereto. Sampling shall be performed in accordance with techniques approved by the administrator.
  5. Maintenance of records. Any industrial user subject to the reporting requirements established in this section shall maintain records of all information resulting from any monitoring activities required by this section. Such records shall include for all samples:

    1. The date, exact place, method, and time of sampling and the names of the persons taking the samples;
    2. The dates analyses were performed;
    3. Who performed the analyses;
    4. The analytical techniques/methods used; and
    5. The results of such analyses.

    Any industrial user subject to the reporting requirement established in this section shall be required to retain for a minimum of three (3) years all records of monitoring activities and results (whether or not such monitoring activities are required by this section) and shall make such records available for inspection and copying by the city, director of the division of water quality control, Tennessee Department of Health and Environment or the Environmental Protection Agency. This period of retention shall be extended during the course of any unresolved litigation regarding the industrial user or when requested by the city, the approval authority, or the Environmental Protection Agency.

  6. Safety. While performing the necessary work on private properties, duly authorized employees of the city shall observe all safety rules applicable to the premises established by the company and the company shall be held harmless for injury or death to the city employees and the city shall indemnify the company against loss or damage to its property by city employees and against liability claims and demands for personal injury or property damage asserted against the company and growing out of the monitoring and sampling operation, except as such may be caused by negligence or failure of the company to maintain safe conditions. (2011 Code, § 18-209, modified)