Legal Documents of Maryville

Code of Maryville

Maryville
Title 19 : Stormwater
Chapter 2 : Grading, Soil Erosion And Sedimentation Control

19-213 : Documentation kept at the project site.

Owners or operators of land-disturbing activities that require an EPSC or sketch plan shall keep the documentation listed below at the site of the land-disturbing activity from the date that the grading permit is approved to the date of termination of coverage of the State of Tennessee general NPDES permit for discharges of stormwater associated with construction activities, as identified on the Notice of Termination (NOT). Owners or operators with day-to-day operational control over implementation of the EPSC or sketch plan shall have a copy of the plan available at a central location on-site for the use of all operators and those identified as having responsibilities under the plan whenever they are on the site of the land-disturbing activity:

  1. A copy of the approved EPSC or sketch plan;
  2. Documentation of inspection of the erosion prevention and sediment control practices located on the site of the land-disturbing activity, prepared in accordance with the inspection documentation requirements of State of Tennessee general NPDES permit for discharges of stormwater associated with construction activities; or
  3. Any other records required by the Tennessee general NPDES permit for discharges of stormwater associated with constructed activities. (1999 Code, § 19-313)