19-211 : Pre-construction inspection and meeting.

  1. For all land-disturbing activities greater than one-tenth (1/10) acres, a grading permit shall be issued only after a pre-construction inspection by the director of engineering and public works, or his/her designee, indicates that perimeter erosion prevention and sediment control measures have been installed in accordance with the approved plan.
  2. Attendance at a pre-construction meeting with the director of engineering and public works, or his/her designee, prior to issuance of a grading permit is required for owners and operators of developments or redevelopments that are:


    1. New residential subdivisions;
    2. A priority construction activity, as defined in this chapter; or
    3. Will discharge stormwater runoff to exceptional Tennessee waters.
  3. Owners and operators of land development activities not listed in subsection (2) of this section may be required to attend a pre-construction meeting when coordination with adjacent construction activities is needed or when conditions indicate a higher than normal risk for pollutant discharges. (1999 Code, § 19-311)
Date Last Updated: 12/22/2025
Codification Date: 06/01/2024

Officials at Date of Last Codification:

Mayor - Andy White
Vice-Mayor - Fred Metz
Council Member - Sarah Herron
Council Member - Tommy Hunt
Council Member - Drew Miles
City Manager - Greg McClain
Assistant City Manager - Kevin Stoltenberg
City Recorder/Financial Services Director - Sherri Phillips
City Attorney - Melanie Davis