Engineering Fees

Print This PagePrint This Page Send by EmailSend by Email
Reviewed Date: October 25, 2016

Original Author: 
Rollins, Sharon
Date Created: 
Jun 13, 2006


Subjects:
Engineers

Engineering Fees

Summary: 
MTAS was asked for information on determining engineering fees.

Knowledgebase-Engineering Fees

Notes on Engineering Fees
by
Sharon Rollins, P.E., MTAS Public Works and Engineering Consultant


Please see Qualification Based Selection, MTAS Guide for Procuring Professional Engineering Services in Tennessee, by Sharon Rollins. Pages 9-10 discuss the types of fees generally applied. They are (1) salary cost times a multiplier plus direct non-salary expense, (2) per diem, (3) cost plus fixed fee, (4) lump sum and (5) percentage of construction cost. The complete publication is available at:

www.mtas.utk.edu

For projects funded by the TN Department of Economic and Community Development, information on engineering fees is available from ECD’s web site at:

http://tennessee.gov/ecd/CDBG_handbook.html

The State Building Commission also offers information on design fees at the following web site:

http://www.state.tn.us/finance/rpa/archit.shtml

You specifically requested information on engineering fees as a percentage of construction costs for transportation projects. Although the percentage of construction costs method has been widely used, it is not recommended because studies show that no clear relationship exists between engineering costs and construction costs.

The American Society of Civil Engineers previously published curves for engineering costs as a percentage of construction costs. But, they no longer publish those curves because an antitrust settlement between the U.S. Justice Department and professional societies determined that the fee curves would no longer be published. (see attached).
The Tennessee Society of Professional Engineers also published a curve relating engineering costs to construction costs at one time. But, they have discontinued as well (see attached).

In summary, I suggest that you consider basing engineering fees on a method other than percentage of construction costs. If MTAS may provide assistance, please call.

Reference Document(s): 

Attachment(s):

More Like This


About Our Knowledgebase

MTAS letters and publications were written based upon the law at the time and/or a specific sets of facts. The laws referenced in the letters and publications may have changed and/or the technical advice provided may not be applicable to your city or circumstances. Always consult with your city attorney or an MTAS consultant before taking any action based on information contained in this database.